34 metre high surge tank to be completed in Chilime Project

January 5, 2000
1 MIN READ
A
A+
A-

Rasuwa, Jan. 5: A 34-meter high surge tank is to be completed in the middle portion of the Chilime Underground Hydro Electrict Project at a cost of Rs 3,200,000, it is stated by the project.

The outlay for the project under which a dam will be thrown across the Chilime stream and the flow released at Syafubesi is Rs 2,320 million.

Digging work has been completed on 470 meters of a 2,826 meter road to be built from Chilime to Syafu.

The project which is scheduled to be completed in July will produce l37 million units of electricity and generate an annual income of Rs 500 million.

Manager Dr. Dambar Bahadur Nepali said so far about Rs 500 million has been spend on the project.